You can create, update and remove activities directly on the Timeline.

Starting with blank timeline

...

Dominik M. (Unlicensed) we need to show how it looks, starting with blank timeline.

...

Right after you publish the page with new macro you should see empty timeline waiting for you.

Image Added

Use blue button "Create +" and start adding items to timeline right away.


Adding a new activity entry

...

If you prefer not to have a stiff Start/End Date set, then "Duration: (4) is a better option. Here you can set how many hours should it last (as it fits better particular time-oriented tasks).

(info) In regards to "Duration" - be advised: only working day (business) hours are taken into consideration, so activity with i.e. 16 hours may look extended like it is 3 days long on the graph, whilst only 8 hours of each day are taken into account from time frame 8 AM to 6 PM. 

Additional comment to the assignee's activity may be left as well (5).

...

If you want to do some bulk actions then consider ticking "Create another" (6). If all is ready and set correctly please use "Create" (7) button to place it in timeline view.

Update an Entry

To update an existing entry click on it and drag for a given period - this method suits the best for minor changes. To use drag and drop technique first you need to select an item, using single left mouse button click. For major changes simply double click an item to open its full edition.

(info) The easiest way to spot if the element was selected is to see if red "x" symbol is visible on its right side (1). After selecting an item on the timeline, its frame color also changes (you should be able to spot its border yellow glow)

Image Modified

Dialog with summary of changes appears after using either double click or drag and drop technique:

Image Modified


Delete Entry

...